Project
Relief camp project, 2023
Two thousand metal bunk beds and two thousand steel lockers, from a proforma signed on 23 March 2023 to the main volume delivered on 8 May.
- 4,000Units produced
- 46 daysProforma to main volume delivered
- 37Truckloads
- 4Deliveries to site
The order
The proforma was confirmed on 23 March 2023 for 2,000 metal bunk beds and 2,000 two-door steel lockers, delivered to site rather than to a depot.
The lockers were the 2-Door Steel Locker from our catalog, unchanged. The bunk bed was not a catalog model. It was based on the Economic Metal Bunk Bed, with two guardrails instead of one and the bed base cross members made demountable rather than welded.
The calendar the order ran through
Ramadan ran from 23 March to 20 April in 2023. The proforma was signed on its first day. Eid al-Fitr fell on 21, 22 and 23 April, three days of public holiday in Turkey, with 20 April a half day. The first shipment left on 24 April, the day after Eid ended.
This is worth knowing if you are planning your own timeline. A Turkish production window that overlaps Ramadan and Eid is not the same window as one that does not.
Four deliveries
| Date | Bunk beds | Lockers |
|---|---|---|
| 24 April 2023 | 600 | 600 |
| 26 April 2023 | — | 200 |
| 29 April 2023 | 200 | 1,200 |
| 8 May 2023 | 1,200 | — |
The main volume was delivered on 8 May, 46 days after the proforma.
Transport
The order moved on 37 truckloads, 26 of lockers and 11 of bunk beds.
On site
Deliveries went to the camp itself. Parts were staged under the tents they would be built in.
Assembly
Assembly was not in the original scope. When the deliveries began the buyer asked us to take it on, so we organized a crew on site and coordinated the build ourselves. SOURESA was on site while it ran.
Installed
The bunk beds ran down both sides of a tent, with the lockers set against the wall. The lockers arrived assembled, so they were placed rather than built.
Taken down again, 2024
The camp came down between 1 July and 29 August 2024. We took apart the 2,000 bunk beds and 2,000 lockers we had supplied the year before, packed them into cases, and loaded them out. Our share of the removal logistics came to around 91 truckloads, tents and camp materials included, coordinated in about three weeks.
The cases were our design. The buyer needed the beds back in store rather than scrapped, and loose components take a lot of floor space. A collapsible steel case holds ten bunks. Full or empty it stacks, and empty it collapses down small, so a store that would have been full of frames holds cases instead.
Packing a case takes longer than throwing components on a pallet, and that is the point. Every part is placed, so a short case shows itself before it leaves. After that the counting stops. Fifty beds to a site is five cases, and nobody at either end is checking whether a guardrail went missing on the way.
The bunks had been in service for a year. They came apart in the condition they were installed in, frames and welds intact, and went back as components rather than as scrap. The buyer is using them again, on other sites. That is one project on one date rather than a tested figure, and it does not stand in for the load test we have not had done.
The site
The delivery address was a NATO relief camp.
Talk to us about your project
Send us the quantity, the destination, and the date you need it on site, and we'll prepare a quote, usually within 24 hours.